Client: RTA
Operator: SERCO
Engineer: SYSTRA
Main Contractor: Alstom/Besix
The Dubai Tram (previously the Al Sufouh Tram) system was designed to be an integral part of the Dubai transport network, linking the Dubai Metro and the Palm Monorail and running along Al Sufouh Road and Jumeirah Beach Road from Mall of the Emirates at one end to the Dubai Marina. In 2013 Sheikh Mohammed officially unveiled the designs for the interiors of the trains and of the stations and plans were made to up, the system is programmed to be fully operational by November 2014. Karma were appointed as Commissioning Managers and our site team’s task was to manage all the MEP services commissioning activities on the project working for the main contractor, managing 3 separate MEP Contractors.